SOURCING COMPARISON / 01

Domestic vs. Imported Fasteners:Compare Landed Cost, Lead Time, and Release Terms

Domestic stock can cover a short release window. A planned import can cost less on repeat volume if the unit savings cover freight, duty, and extra inventory. The next release and the annual buy don’t have to come from the same source.

FIG. 01   /   OCEAN FREIGHT

Domestic and imported fasteners, side by side

Use the same drawing revision, annual usage, and required dock date for both quotes.

Purchasing terms to compare for domestic and imported fasteners
Purchasing termDomestic sourceImport source
Landed costDelivered price for the release quantity. Is freight included?Factory price plus freight, duty, brokerage, and delivery to the same dock. Exclude charges already in the quote.
Lead timeAvailable stock versus a new production run. Which quantity has a committed dock date?Stock staged or in transit versus a new mill shipment. Offshore’s typical planning window for a new shipment is 90–150+ days, not a commitment for a specific part.
Release termsRelease minimum, blanket order term, and who owns any balance when the agreement ends.Factory minimum, shipment size, staged releases, and when title passes to the buyer.
Inventory exposureSmaller releases can reduce cash tied up in stock. A noncancelable blanket can still commit the full volume.A larger lot may lower unit cost but increase carrying cost. Supplier-held inventory may change that trade-off.
Origin & eligibilityA U.S. ship-from address does not establish U.S. manufacture. Compare documentation against the specification.If U.S. manufacture is mandatory, a foreign-made equivalent is not eligible, regardless of price or where it is stocked.

What does a 2¢ unit-price difference buy?

Suppose the domestic quote is $0.20 per fastener and the import quote is $0.18, before separately billed costs. At 100,000 pieces per year, the lower unit price leaves $2,000 per year to cover the import option’s additional costs.

100,000 pieces × ($0.20 − $0.18) = $2,000

If importing adds $1,200 in freight, duty, and fees over the domestic option, the landed-cost advantage is $800. If the larger lot adds $500 in annual carrying cost, the remaining advantage is $300 for the year. At $2,000 in total additional costs, the options break even; above that, the domestic quote costs less overall.

Assumptions behind the example

  • Both quotes meet the same specification, quality requirements, and delivery schedule. All 100,000 pieces are used within the year.
  • Every dollar figure is illustrative, not a tariff rate, supplier quote, or savings forecast. Compare to the same dock and count each cost only once.
  • Carrying cost is separate from landed cost. Tooling, qualification, and expedites are excluded here; any additional first-year cost above the remaining $300 reverses the first-year result.

For the next release

If the next release is due before a new mill shipment can arrive, price available stock for that release and compare the remaining annual volume separately.